eipproofQueue
Snapshot 2026-11-06, open for snapshot details

as of 2026-11-06T22:33:32Z

forkGlamsterdam · EL
newest EELStests@v21.0.2
hivehive listing 999 runs
archived snapshot 2026-11-06T22:33:32Z, shown with the current code and proofs · latest data · all snapshots

Start here

Three questions a core dev asks, a minute each. Every number comes from the snapshot shown at the top.

What is my client missing today?

Open your client. Its To do list puts the most important item first.

Nethermindrun v21.0.2 (15 EIPs)
Gethrun v21.0.2 (15 EIPs)
Rethrun v21.0.2 (15 EIPs)
ethrexrun v21.0.2 (15 EIPs)
Besurun v21.0.2 (15 EIPs)

Is this EIP really done?

Done means: the client's latest hive run on the newest EELS release passes, and every EIP change since the version EELS implements is proven by a test or marked wording-only. Anything else stays open.

EIP-2780reduce intrinsic tx gas5 on old tests · matrix row
EIP-7708eth transfer logs5 on old tests · matrix row
EIP-7778block gas accounting without refunds5 on old tests · matrix row
EIP-7843slotnum5 on old tests · matrix row
EIP-7928block level access lists5 on old tests · matrix row
EIP-7954increase max contract size5 on old tests · matrix row
EIP-7976increase calldata floor cost5 on old tests · matrix row
EIP-7981increase access list cost5 on old tests · matrix row
EIP-7997deterministic factory contract5 on old tests · matrix row
EIP-8024dupn swapn exchange5 on old tests · matrix row
EIP-8037state creation gas cost increase5 on old tests · matrix row
EIP-8038state access gas cost increase5 on old tests · matrix row
EIP-8070sparse blobpool5 on old tests · matrix row
EIP-8246selfdestruct no burn5 on old tests · matrix row
EIP-8282builder execution requests5 on old tests · matrix row
EIP-7688Forward Compatible Consensus Data Structuresno tests yet · matrix row
EIP-7732Enshrined Proposer-Builder Separationno tests yet · matrix row
EIP-7904Compute Gas Cost Analysisno tests yet · matrix row
EIP-7975eth/70 - Partial Block Receipt Listsno tests yet · matrix row
EIP-8045Exclude Slashed Validators from Proposingno tests yet · matrix row
EIP-8061Increase Exit and Consolidation Churnno tests yet · matrix row
EIP-8136Cell-Level Deltas for Data Column Broadcastno tests yet · matrix row
EIP-8159eth/71 - Block Access List Exchangeno tests yet · matrix row
EIP-8189snap/2 - BAL-Based State Healingno tests yet · matrix row
EIP-8261Gas Limit Scheduleno tests yet · matrix row

What do I tell the test team?

Each item names an EIP and the tests it needs. Every EIP page has a Copy as Markdown button for the message.

25 items: update tests (15), write tests (10). Open the test team list.